1. Business Development & Coordination with Business Development
Department Contacting potential clients to establish rapport and arrange meetings. Identify and develop new & existing business partnership opportunities within the construction industry. Work closely with ED & BDD Director to find and develop new markets and improving sales Understand the client/Owner challenges, provide our Technical support service help client/Owner to outcome these challenges. Planning and overseeing new marketing initiatives.
3
2. Proposal Preparation and Coordination with Proposal Team Support in tender preparation and review the proposal for submission. Provide project experience to Tender team for the proposal preparation. Attending Tender Clarification with Proposal Team Provide market rates to the tender team for the proposal preparation. Train Leads/Engineer to involve for the tender preparation and follow through the tender process.
4
3. Engineering Management & Coordination with Engineering Department Involve
for
the
Engineering
design
review
during
tender
stage
and
provide
recommendation for the optimization in term of costing and constructability. Review Critical detail design to further optimize with increase the Profitability in overall. Follow up with engineering team for any Site technical related issue until proper close up. Provide Engineering/Technical Solution to meet Client/Owner’s needs. Residual engineering shall be handled by the Field engineering team Ensure final closure documents to be submitted in time
5
4. Client Management & Coordination Address Client/Owner’s concerns in a timely manner. Identify Client/Owner’s needs and wants Build long-term relationships with key clients Maintain high standard in safety and achieve incident free work place Meet and achieve customer satisfaction above 80% Follow up on upcoming Variation orders in project and new upcoming projects.
6
5. HSE Management and Coordination with Corporate HSE Department Provide full support for Corporate HSE award preparation and achievement. Encourage HSE team to implement safety programme for construction activities Review and comment on existing HSE system to improve the operation time to time. To instil ownership priority & timely manner at our culture to work safe and achieve higher quality. Guide to HSE team to ensure that adequate information and training are provided to supervisors and workers to make smooth execution at site 7
6. Quality Management and Coordination with Corporate QA/QC Department To demonstrate Quality Leadership to the project team Guide our Quality Team to fulfilling customer contract expectations in quality. Provide full support for Corporate Quality event Responsible & accountable to ensure compliance with company, client's policies and procedures Encourage Project QC team to conduct project specified training to improve project Quality and employee skill quality..
8
7. Procurement & Coordination with Procurement Department Discuss with Procurement team and project team to set up the strategy of procurement, set target at project initial stage and met/higher than the target after completed of the project. Maintain good relationship with Supplier and Vendor always. Review the procurement progress in regular basis and ensure inline with project overall schedule. Always looking for internal surplus material before ordering. And pass down this concept to project team as well. Communicate relevant Information regarding client’s requirement and expectations to procurement while buying products. 9
8. Construction Planning & Execution & QS Management Set Project PI (Productivity Index) with Construction team prior commence of construction. And Brief to the construction team on the PI and reporting in Smart Construction system. Looking on innovative solution to improve productivity at site Manpower & Resources Planning inline with overall project schedule and needs. Regularly to attend site visit and understand the project status. Monitoring budget and Cash flow, review with project team in regular basis and discuss how to increase project value and improve project margin. Assign QS team to track the Change Order at project. By briefing the project scope to construction team, make them fully aware what are our scope and getting more Change Order from client. Attend Project Sponsor Meeting to get feedback from Client/Owner’s on the project team performance.
10
9. Training and Coordination with Corporate Training Department Review and comment on the training material to make the training more effective and meet the objective. Manage and Ensuring to conduct 72 hours training programme at project site members with right training to right personnel Assign relevant person attending required training to improve the skillset. Monitor
the
performance
after
the
training
to
evaluate
the
training
effectiveness. Feedback to Corporate training team if need to improve on the training process. Arrange Supplier/Vendor training to improve the skillset on products. Arrange necessary internal & external training to the potential people. 11
10. Construction Equipment Monitoring To coordinate with REI equipment store assisting in project team for construction equipment planning and temporary site office equipment mobilization Assist in REI overall construction Tools & equipment database updating in Hilti ON track system and monitor equipment and tools availability for the project operations Coordinate with project QA/QC & HSE teams for measuring & testing equipment database update and monitor availability for project operations. Construction Vehicle's are monitoring through Fleet management.
12
11. Resource Planning & Innovative improvements Manpower & Resources planning inline with overall project schedule and needs. Set PI with correct crew to the work, monitor through the Smart construction. Looking at Overall REI manpower status, arrange for recruitment as per manpower demand (Include considering of potential project). Research new type of tools/equipment to improve current work process. Getting update on the regulations from Government and set up the program to adopt/utilize these changes/funds.
13
12. Reports Regular basis to provide report/project update to the Directors and discuss on the strategy if need to change. Ensure project team provide regular report/project updates in order to monitor the project program. Review Finance report to understand the company finance status. Ensure project team submit the monthly management report on time. Ensure project team understood the reporting channel to Corporate and Client as well.
14
Implemented & Follow up in NESTE & SMOP projects: Smart Construction Hilti On Track Online Declaration Forms Virtual Trainings Fleet Management
& Identify and Implement New innovative methods and Mechanism to get good productivity to save the man hours.
15
Year
EPC
Construction Maintenance Value Added
Projects
2013
1
EVONIK ME5
2014
1
EVONIK ME5 & ARKEMA
2015
1
ARKEMA & AFTON PHASE-1
2016
1
SRC - MCP
2017
1
SRC - MCP & EVONIK ME6
2018
0.85
2019
1
LINDE / SMOP
2020
1
NESTE / SMOP
0.15
EVONIK ME6 / WWTP
2021
NESTE / SMOP
Total
7.4 YEARS 0%
98.1%
0%
1.9%
100% 16
Strengths Handle Projects related to 4 pillars Handle Multiple Construction Projects with integrity
Weaknesses Need to learn and act effectively in the bidding coordination for the major projects.
17
Ensure every project completed with above 80% of customer satisfaction feedback. To register REC as a Residential Contractor in SMOP yard. Train potential Deputy Project Manager / Site Manager / Project Engineer and 2 QS. To complete the project within the targeted man hours and committed margin.
18
4 Pillars
EPC
Construction
Maintenance
Value Added
Construction Projects & MEI Projects Become a part of the key Project Management team and reach to achieve heights at Senior Project management level (Project Director). Presently handling Construction projects with the value of more than 40 million and eager to learn more , involve and perform in EPC Projects. Target – 5 Years
19
Key Performance Indicators
Method of Measurement
1. Compliance with company and project standard on health and safety requirement
To achieve 0 LTI in overall project in a year
2. Project Equipment, Material &
To achieve 2% savings against budgeted amount for procurement of Equipment, Material & Services
Services Procurement
Project Execution 3. Project Budget, Man hours & Profit
4. Variation Orders from Clients to increase Project Revenue
To ensure to complete the project within 1.5% targeted man-hours from Initial Budget To achieve minimum 10% variation orders value from original contract value per project
20
Key Performance Indicators
Method of measurement
1. Identify the Potential peoples from our team to bring to next Attached Project Potential Name list level. Microsoft Excel Worksheet
Team Building (Mentoring & Training)
Provide required trainings and support to the teams to develop to Middle management level.
21
2. Provide required trainings and support to the teams to develop
Provide adequate and sufficient training to achieve the developments.
SAFETY, QUALITY & SKILL development. Arrange vendor trainings to develop our team knowledge. To achieve 72hrs training within the
Team Building (Mentoring & Training)
year for all the employee’s. Provide Training and Mentor to our employees to achieve our company vision.
22
Key Performance Indicators
Method of Measurement
1. To implement innovative methods & Identify and Implement new innovative mechanism mechanism to improve the productivity by manpower reduction- In Progress 2. To register our company in SMOP as We will register our company as RC. Residential Contractor in SMOP within this year. Through this we can able to get projects continuously in priority.
Company Development & Improvement
3. Hilti On Track , Fleet Management, Virtual Trainings , Smart Construction and Data development
Implemented at site and In progress
4. Workshops &Committees (Quality, To conduct workshops & committees to Safety ,Productivity & Project network and gain exposure to wide Management) knowledge base to our team.