FDCD 2017 Fiscal Year OBO Capital Project and Task Orders Awards
A/E Design Awards Post & Project Location
Brasilia, Brazil
Award/Order Number Contract + Task Order
SAQMMA17C0017
AWARD AMOUNT:
$24,573,903.00
AWARD DATE/ Duration
09/25/17, 565 calendar days
Page 1 of 10
CONTRACTOR NAME & Address
CO & PROJECT DESCRIPTION
Studio Gang Architects 1520 Division Street Chicago, IL 60642
Brian Mulcahy; New Embassy compound design
Major Construction
Post & Project Location
Contract Number
SAQMMA17C0079 Beirut, Lebanon
Ankara, Turkey
Manila, Philippines
Asuncion, Paraguay
SAQMMA17C0045
AWARD AMOUNT: 1 CLIN 0001 2 CLIN 0002 (VAT) 3-5 Add’l CLINs
CLIN 001 $582,477,230.00 CLIN 002 $27,548,602.00 CLIN 003 $3,584,630.00 Total: $613,6 10,462.00 CLIN 001: $217,467,116.00 CLIN 003: $509,384.00 Total Contract Award: $217,976,500.00
SAQMMA17C0018
CLIN 001 = $136,649,769.00 Contract Award = $136,649,769.00
SAQMMA17C0082
CLIN 001 $156,105,000.00 CLIN 004 $9,718,000.00 Total Contract: $165,823,000.00
DESIGN BUILD AWARD DATE/ Duration
CONTRACTOR NAME & Address
Awarded on B.L. Harbert 12/30/2016; Duration – 210 London Parkway 58 months Birmingham, AL 35211
B. L. Harbert International, LLC. 210 London Parkway Birmingham, AL 35211
23 Dec 2016; 36 months
PREQUAL CO & VS. PROJECT Design Partner BIDS DESCRIPTION & Address REC’D
Beirut New Embassy Complex NA
3 vs 2 CO: Adam Hiland
8 vs 4
Ankara New Embassy Complex
NA CO: Zaldy Sabino
Framaco International, Inc. 800 Westchester Ave, Ste. S430 Rye Brook, NY 10573
20 Dec 2016; 42 months
01/31/2017; 1460 calendar days
Caddell Construction Co. (DE), LLC 2700 Lagoon Park Dr. Montgomery, AL 36109
Page 2 of 10
NA
NA
8 vs 4
9v3
Manila, Philippines New Embassy Complex CO – Ariana Nazario. Project: Construction of the New Embassy Compound (NEC) in Asuncion, Paraguay.
Post & Project Location
Erbil, Iraq
AWARD AMOUNT: 1 CLIN 0001 Contract Number 2 CLIN 0002 (VAT) 3-5 Add’l CLINs CLIN 001 Construction $402,487,364.00 CLIN 002 VAT - $0 CLIN 003A Housing $12,712,491.00 CLIN 004 – Security $6,114,787.00 SAQMMA17C0212 CLIN 005 – Training $155,737.00 CLIN 006 – Landscape $500,000.00 CLIN 007 – Allowance For Reimbursement $500,000.00 TOTAL: $422,470,379.00
DESIGN BUILD AWARD DATE/ Duration
June 30, 2017; Duration – 42 months from NTP
CONTRACTOR NAME & Address
B.L. Harbert International, LLC
820 Shades Creek Parkway, Suite 3000 Birmingham, AL 25209
PREQUAL CO & VS. PROJECT Design Partner BIDS DESCRIPTION & Address REC’D
EYP, Inc. 201 Fuller Road – Fifth Floor 5v2 Albany, NY 12203
Montevideo, Uruguay
CLIN 0001 $86,644,145.00 SAQMMA17C0244 CLIN 0002 $4,813,135.00 Total: $91,457,280.00
Nicosia, Cyprus
CLIN 001 – $20,517,499.00 09/26/2017; 973 Williams Building Company CLIN 002 – $0.00 days from issuance 196 Old Town House Road SAQMMA17C0291 CLIN 003 – $75,000.00 of NTP W. Yarmouth, MA 02673 CLIN 004 – $420,000.00 Total: $21,012,499.00
NA
Kampala, Uganda
CLIN 0001 $130,675,411.00 Sep 29, 2017; SAQMMA17C0319 CLIN 0002 (VAT) 41 Months from $7,328,026.00 date of NTP Total: $138,003,437.00
EYP 1000 Potomac Street, NW Washington, DC 20007
August 10, 2017 Duration: 40 Months
Perini Management Services, Inc. NA 73 Mt. Wayte Avenue Framingham, MA 01701
Pernix Group 151 E. 22nd Street Lombard, IL 60148
Page 3 of 10
CO: Adam Hiland Erbil, Iraq NCC
CO: Chrissie Fields 5 vs 3
Chancery Major Renovations CO: Ronette C.
McBean-Felder 10 v 6
D/B/B Nicosia CSU
CO: James Waggoner 7v4
D/B Kampala, Uganda NOX
Khartoum, Sudan
SAQMMA17C0293
CLIN 001: $15,368,498.00 CLIN 002: $853,644.00 CLIN 003: $45,630.00 CLIN 004: $27,170.00 CLIN 005: $53,700.00
Total: $16,348,642.00
Ciudad Juarez, Mexico
Dhaka, Bangladesh
Mexico City, Mexico
SAQMMA17C0295
SAQMMA17C0296
SAQMMA17C0287
Sept. 29, 2017; 24 months from date of NTP
CLIN 0001: $13,767,714.00 September 30, 2017; CLIN 0002: $902,400.00 34 months Total: $14,670,114.00
CLIN 001: $24,104,007.24 CLIN 002: $1,800,001.00 September 29, 2017; 26 months from date Total: $25,904,008.24 of NTP
CLIN 001: $518,276,000.00 CLIN 002: $36,446,533.00
09/29/2017 – 50 Months
Total: $554,722,533.00
Athens, Greece SAQMMA17C0314
CLIN 0001: $206,641,000.00 0003: $353,000.00 0004: $125,000.00 0005: $206,000.00 0006: $239,000.00 0007: $95,000.00 0008: ($130,000.00) 0009: $102,000.00 Total - $207,631,000.00
09/29/2017 – 48 Months
CO: David Vivian CS: Sam Koelbl
Montage, Inc. 3636 16th St. NW #AG-50 Washington, DC
EMR 4511 Daly Drive, Suite A Chantilly, Virginia 20151
Desbuild 4744 Baltimore Ave. Hyattsville, MD 20781-2225
Caddell Construction Co. (DE), LLC 2700 Lagoon Park Drive Montgomery, AL 36109
Caddell Construction Co. (DE), LLC 2700 Lagoon Park Drive Montgomery, AL 36109
Page 4 of 10
8 vs 3 Khartoum, Sudan MSGR Renovation KCCT 1200 Connecticut Avenue NW, Suite 1250 Wash DC, 20036 KCCT 1200 Connecticut Avenue NW, Suite 1250 Wash DC, 20036
CO: David Vivian CS: Donna Neal 12 v 6
Cuidad Juarez New MSGR
CO: Donna Neal 6v6
Compound Security Upgrade
CO: Jim Thomas/Ariana Nazario 5v2 Mexico City NEC
CO: David Vivian; CS: Jen Leung 4v2
Design/Bid/Build Athens Compound Major Rehab
Nairobi, Kenya
SAQMMA17C0334
CLIN 1 $151,634,000.00 CLIN 2 $ 0.00 CLIN 3 $1,500,000.00 Total $153,134,000.00
09/30/2017; 43 months from date of NTP
Caddell Construction Co. (DE), LLC 2700 Lagoon Park Drive Montgomery, AL 36109
Integrus Architecture 10 South Cedar Spokane, WA 99201
CO: Jim Thomas CS: Carly Sweet
6 v2 Nairobi
Guatemala City NEC Guatemala City, Guatemala
SAQMMA17C0325
CLIN 0001 $287,607,771.00
B.L. Harbert Awarded on 210 London Parkway 09/30/2017 Duration – 52 months Birmingham, AL 35211
Page 5 of 10
CO: Lily Savic PSP
4v2
Task Orders Post & Project Location
Task Order Number
SAQMMA17F0493 Beirut, Lebanon
Antananarivo, Madagascar
Muscat, Oman
SAQMMA17F1281
SAQMMA17F2449
AWARD AMOUNT: 1 CLIN 0001 2 CLIN 0002 (VAT) 3-5 Add’l CLINs CLIN 001: $16,237,253.88 CLIN 002: VAT $659,445. 12 CLIN 003: HATS shipping $248,874.12 Total: $17,145,573.12
CLIN 1-$834,601.00 CLIN 2-$9,799.00 CLIN 3-$22,952.00 TOTAL:$867,352.00
CLIN 001: $3,089,159.50 CLIN 002: $90,000.00 Total: $3,179,159.50
Skopje, Macedonia
SAQMMA17F3613
CLIN 1: $ 1,018,564.29 CLIN 2 $5,000.00 CLIN 3 $22,917.71 TOTAL $1,046,482.00
DESIGN BUILD AWARD DATE/ Duration
CONTRACTOR NAME & Address
January 18, 2017; 330 days from date of NTP (February 17, 2017)
VS. BIDS REC’D
CO & PROJECT DESCRIPTION
CO: Adam Hiland Desbuild Limak D&K JV 4744 Baltimore Avenue Hyattsville, MD 20781
4/12/2017; 18 months after Edifice, LLC issuance of 6600 Virginia Manor Rd NTP Beltsville, MD 20705
08/04/2017; 18.5 months from date of NTP issuance
Design Partner & Address
TOPR Ktrs
Desbuild Inc. 4744 Baltimore Ave. Hyattsville, MD 20781-2225
09/18/2017; Edifice, LLC 540 days after 4328 Farragut Street issuance of Hyattsville, MD 20781 NTP
Page 6 of 10
NA
7 Rec’d
NA 3 Rec’d
Temporary Construction Support Facilities (tCSF)
CO/CS: James G. Thomas Jr./ Kellie Herschler/Carly Sweet FEBR R&R
CO: Jim Thomas CS: Deborah Carey NA Muscat, Oman MSGQ
NA
3 Rec’d
Skopje, Macedonia FEBR
Post & Project Location
Kingston, Jamaica
Contract Number
SAQMMA17F3617
AWARD AMOUNT: 1 CLIN 0001 2 CLIN 0002 (VAT) 3-5 Add’l CLINs CLIN 1 CLIN 2 CLIN 3 TOTAL
$2,654,952.24 $5,000.00 $53,099.04 $2,713,051.28
DESIGN BUILD AWARD DATE/ Duration
CONTRACTOR NAME & Address
09/18/2017 ; 540 days after issuance of NTP
Hardline-Nati Construction LLC 9015 Rhode Island Avenue College Park, MD 20740
Sarajevo, Bosnia and Herzegovina
HNC SAQMMA17F269 8/16/2017 4221 Forbes Blvd 2 CLIN 001: $1,377,759.44 Lanham MD 20706
Riga, Latvia
ICS SAQMMA17F353 CLIN 001: $2,079,195.00 9/18/2017 429 N. Main St. 8 Memphis, TN 38103
Khartoum, Sudan
Singapore, Singapore
SAQMMA17F387 CLIN 001: 7 $1,177,954.05
SAQMMA17F405 CLIN 001: 3 $2,341,656.31
Edifice Solutions 9/22/2017 6600 Virginia Manor Rd Beltsville, MD 20705 Edifice Solutions 9/22/2017 6600 Virginia Manor Rd Beltsville, MD 20705
Page 7 of 10
Design Partner & Address
PREQUAL VS. BIDS REC’D
CO & PROJECT DESCRIPTI ON
Kingston, Jamaica FEBR
NA
3 Rec’d
NA
3
NA
2
NA
3
CO: Lars Hankin
NA
3
CO: Lars Hankin
CO: Lars Hankin
CO: Lars Hankin
Bangui, Central African Republic
Hong Kong, SAR
CLIN 001: SAQMMA17F4287 $4,985,988.00 001 for design $328,191.00; 002 for construction $3,563,935.68 SAQMMA17F4079 003: $39,421.00 Total: $3,931,547.68
Freetown, Sierra Leone
SAQMMA17F4531
CLIN 001: $9,451,760.53 CLIN 002: Bonding: $17,000.00 Total: $9,468,760.00
Edifice Worldwide 9/26/2017 6600 Virginia Manor Rd Beltsville, MD 20705
September Edifice Solutions 27, 2017; 6600 Virginia Manor Rd 18 months Beltsville, MD 20705 from LNTP
September 27, 2017 (POP : 200 days)
Armature Group
2
E.K. Fox Engineers 4035 Ridge Top 4 vs 3 Road, Suite 650 Fairfax, Virginia 22030
CO: Lars Hankin
CO: Jim Thomas CS: Jimmy Lai
Chillers/ HVAC Upgrade CO: Sharon McCaulay
Tidewater, Inc 6625 Selnick Dr. – Ste A Elkridge, Maryland 21075
Freetown Chancery PCC Repairs CO: Sharon MaCaulay
Conakry, Guinea
Bogota, Colombia
SAQMMA17F4575
CLIN 001: $828,620.14
SAQMMA17F4122
CLIN 001-$44,635.00 CLIN 002 $50,150.00 CLIN 003 $1,284,203.00 Total: $1,378,988.00
Tidewater, Inc 6625 Selnick Dr. – Ste A Elkridge, Maryland 21075
9/25/17, 12 months
CLIN0001 = Construction Services $4,999,881.00 Rio de Janeiro, Brazil
SAQMMA17F4854
09/29/2017 CLIN 0002 VAT: $245,001.00
Conakry Chancery HVAC Repairs CO: Alla Weinstein
Greenway Enterprises, Inc.
HCG-ICS 2154 Hillshire Circle Memphis, TN 38133
2v2
NA
Fire Alarm replacement Rio Chilled Water and Electrical System Upgrade CO: Lily Savic
Page 8 of 10
Design Contracts
Brasilia, Brazil
$24,573,903.00 0 0
Design Contract Total
Freetown, Sierra Leone Conakry, Guinea Bogota, Colombia Rio de Janeiro, Brazil Task Order Awards Total
Erbil, Iraq
$613,610,462.00 $217,976,500.00 $136,649,769.00 $165,823,000.00 $422,470,379.00
Montevideo, Uruguay Nicosia, Cypru
$91,457,280.00 $21,012,499.00
Kampala, Uganda Khartoum, Sudan Ciudad Juarez, Mexico Dhaka, Bangladesh Mexico City, Mexico Athens, Greece Nairobi, Kenya Guatemala City, Guatemala Construction Contracts Total
Task order Awards Beirut, Lebanon Antananarivo, Madagascar Muscat, Oman Skopje, Macedonia Kingston, Jamaica
Construction Contracts Total Task Order Awards Total
Grand Total
$138,003,437.00 $16,348,642.00 $14,670,114.00 $25,904,008.24 $554,722,533.00 $207,631,000.00 $153,134,000.00 $287,607,771.00
$3,067,021,394.24
$17,145,573.12 $867,352.00 $3,179,159.50 $1,046,482.00 $2,713,051.28
Sarajevo, Bosnia and Herzegovina Riga, Latvia
Khartoum, Sudan Singapore, Singapore Bangui, Central African Republic
Hong Kong, SAR
$57,521,967.52
$24,573,903.00 Design Contract Total
Construction Contracts Beirut, Lebanon Ankara, Turkey Manila, Philippines Asuncion, Paraguay
$9,468,760.00 $828,620.14 $1,378,988.00 $4,999,881.00
$1,377,759.44 $2,079,195.00 $1,177,954.05 $2,341,656.31 $4,985,988.00 $3,931,547.68 Page 9 of 10
$24,573,903.00 $3,067,021,394.24 $57,521,967.52
$3,149,117,264.76