Data Loading...
Errors and Omissions - Illinois State Toll Highway Authority Flipbook PDF
2 Reasons contracts and plans change Errors and omissions defined Tollway process Successful design track record Minimal
125 Views
34 Downloads
FLIP PDF 301.81KB
Errors and Omissions
Finance Administration Operations Committee January 15, 2014
Agenda
2
Reasons contracts and plans change Errors and omissions defined Tollway process Successful design track record Minimal recoverable costs to date Continually seek best practices Discussion
Reasons Plans and Contracts Change Change is common in large capital programs
Accelerated program schedules
Differing site conditions
Unidentified utilities Unidentified and unsuitable soil conditions
Specification changes
Tollway initiated Other agency initiated
Balance final field measurements
Errors and omissions
Miscellaneous (such as weather)
3
Errors and Omissions Defined
Error: An incorrect, conflicting, insufficient or ambiguous plan or specification detail or contract administration action
Omission: A failure to indicate on drawings, specifications or other products of professional service the requirement for a feature, system or equipment necessary for the complete and proper function of a project
4
Tollway Process Contract Cost Change Controls Committee (C5) comprised of representatives from Engineering, Procurement, Finance and Audit reviews all construction contract changes
C5 Committee identifies potential E and O items E and O items of more than $50,000 in construction change value reviewed in detail for possible cost recovery Design consultant notified and provided an opportunity to submit additional information or dispute E and O Chief Engineer makes final determination 5
Excellent Design Track Record
Qualified and professional people performing the work
Perform detailed plan reviews at each design submittal
Manage quantities in construction process effectively
One measure of design success is the cost of changes in construction Percentage of change compared to (CO/EWOs) The Tollway has substantially lower costs of construction changes compared to industry average
total construction costs
Industry average* Illinois Tollway
5 to 10 percent Less than 1 percent
*American Council of Engineering Consultants Library: Model for Qualifying the Impact of Change Orders on Project Costs for US Roadwork, December 2009 6
Minimal Recoverable Costs To Date
Few potential E and O items identified
7
From 2005 to 2013, nearly 15,000 Authorizations to Proceed (ATPs) approved; 243 identified as potential E and O for further evaluation
Recoverable costs are not the total value of the change, but those costs that would not have been incurred had the plans been correct Of the 209 potential E and O items that have been evaluated to date, only $20,000 was identified as recoverable
Continual Review for Best Practices Reviewed recommended process American Association of State Highway and Transportation Officials (AASHTO) and benchmarked local agencies and other states Track changes due to E and O Identify procedure to review significant E and O Arizona Department of Transportation Use committee of experts California Department of Transportation for significant E and O Chicago Department of Aviation Maintain appropriate threshold for E and O review Illinois Department of Transportation Texas Department of Transportation Involve design consultant in Wayne County Airport Authority discussions 8
DISCUSSION
What other best practices should we consider as part of our evaluation of the 2013 E and O items?
Moving forward, what should be the threshold for evaluating recovery of costs?
Is there value in a third-party review that warrants the cost?
9
Appendix
10
Compliance with AASHTO
AASHTO recommended process:
Because litigation is expensive and time-consuming, AASHTO encourages agencies to build methods of dispute resolution into their contracts. These methods should encourage:
11
Discovery – Agency conducts initial review of circumstances Initial notification – Agency notifies consultant, requests their involvement Investigation/decision on liability Notification to consultant Review meeting(s) with consultant Alternative dispute resolution Recovery and collection Litigation
Bringing together all parties quickly Focusing on fixing the design problem first, then addressing cost responsibility and recovery Consulting a state attorney general’s office for information on appropriate alternative dispute resolution procedures Instituting a process that is fair and moves quickly to resolution
Local Agency Benchmarks
IDOT
Consultants notified of liability have 30 days to respond, process and move to dispute resolution if necessary E and O threshold:
Chicago Airport System
Uses reviewing committee that reviews alleged E and O, prepares written analysis and meets with consultants to resolve E and O
Wayne County Airport Authority
12
If construction less than $2 million, E and O amount limited to $20,000 If construction between $2 and $10 million, E and O amount limited to 1 percent of contract If construction greater than $10 million, E and O amount limited to $100,000
Designer pays an administrative service fee of 5 percent of actual cost of each construction change
Arizona DOT E and O
As E and O are identified, ADOT performs a review, notifies the consultant, documents their decision on whether a claim is justified and content of the claim, and provides for consultant administrative review if the matter cannot be resolved (“MGT 00-2…,” Nov. 3, 2000, pp. 2-3).
ADOT will estimate additional costs arising from the E and O based on the amount above that expected in the contractor’s bid had the E and O not occurred.
13
If the additional cost exceeds the lesser amount of five percent of the contractor’s bid or $20,000, ADOT may file a formal claim. The amount of the initial claim will be the additional costs less the threshold value. Any future E and O claims on the project will not be subject to reduction by the threshold value.
Unresolved claims over $100,000 will be forwarded to the attorney general’s office.
CalTrans E and O
As a guideline, contract change orders (CCOs) greater than $200,000 related to design changes, conflicts, ambiguities, errors and omissions and cumulative CCOs exceeding 10 percent of the construction project bid likely warrant further review and the matter is forwarded to the chairperson of the Management Review Panel (MRP).
The MRP submits its recommendation to the chief engineer. If the chief engineer approves further action, he will appoint a representative or team to provide notice to the consultant and enter into informal discussions to resolve the matter. Caltrans’ legal division and the chief engineer will be kept apprised of the status of discussions.
Alternative dispute resolution methods may be considered if agreeable to both parties. The consultant should be allowed to take part in discussions of additional costs due to design liability for which he may be held liable.
If a resolution is not attained, the representative will consult with the legal division and recommend to the chief engineer if additional action should be taken.
14
Texas DOT E and O
Change orders are tagged with a reason code identifying the cause of the change.
If an E and O results in a change order, TxDOT must notify the consultant and give that firm an opportunity to address the matter. The amount of the recoverable cost is that which would not have been incurred had the plans been correct.
The consultant must reimburse these costs in cash; in-kind services by the consultant are not acceptable as payment.
A certified initial notification letter will be sent to the consultant describing the alleged E and O, related additional costs, and references to pertinent events. The consultant will be asked to respond within 30 days. If the consultant does submit payment, it is credited according to the procedural guidelines as a refund of expense on the affected construction project.
If the consultant does not make payment, TxDOT may consider legal action. If litigation is the only remaining recourse, TxDOT will work with the state attorney general’s office.
15
THANK YOU
16