Gantt Chart/Diagram Excel Template User Guide Excel-based simple Gantt Chart Template
This Excel-based template allows a Gantt chart to be easily and quickly developed. You can specify each task start date and/or alternatively specify up to 3 other tasks that must be completed before the task can start. As the project progresses, the chart can be updated to show those tasks completed and those yet to be completed. The template is preconfigured for up to 50 tasks but can be edited to increase this. The Excel template is totally customizable, uses only standard Excel features and contains no macros.
[email protected] 8/29/2013
8/29/2013
GANTT CHART/DIAGRAM EXCEL TEMPLATE USER GUIDE Excel-based simple Gantt Chart Template
INTRODUCTION This Excel-based template allows a Gantt chart to be easily and quickly developed. The template generates a Gantt chart for up to 50 tasks. If required, additional tasks can be easily added as described below. You can specify each task earliest start date and/or alternatively specify up to 3 other tasks that must be completed before the task can start. As the project progresses, the chart can be updated to show those tasks completed and those yet to be completed. Completed tasks or portions of tasks completed are show in green, while tasks or portions of tasks remaining to be completed are show in red as in diagram 1 below.
Figure 1 Gantt Chart
The Excel template is totally customizable, uses only standard Excel features and contains no macros.
www.businesstoolsstore.com Copyright © 2013 The Business Tools Store
1
8/29/2013
USER INSTRUCTIONS Data Input A single worksheet “Data Input” is used to enter all the data required to automatically generate the corresponding Gantt chart. Green text indicates the cells that should be used, while a red border indicated those cells that contain formulae and should not be edited.
Figure 2 Gantt Chart Data Input
ENTERING NEW PROJECTS
Gantt Chart Title: Enter the title in cell I4. This title will be displayed on the chart. Tasks: For each task you wish to have displayed on the chart enter the following:
Task Description. Enter a short description of the task. This will be displayed in the lefthand axis of the chart. Pre-condition 1. Enter any task that must be completed before this task can commence. Pre-condition 2. Enter another task that must be completed before this task can commence, if a second task must be completed. Pre-condition 3. Enter a third task that must be completed before this task can commence, if a third task must be completed. Earliest Start Date. Enter the date, if any, before which this task can not commence. Start Date. Enter the project start date as the start date for the first task. Start dates for the other tasks are calculated based on the finish dates for any pre-
www.businesstoolsstore.com Copyright © 2013 The Business Tools Store
2
8/29/2013
condition tasks if pre-condition tasks have been specified or the earliest start date if an earliest start date has been specified. Where no pre-condtion tasks or an earliest start date are specified the start date for the project, i.e. the start date for the first task, is used. Duration. Enter the total duration of the task in days Completed. For tasks that have commenced the numbers of days of the task that have been completed should be entered. Remaining. The number of days remaining to complete the task is calculated by subtracting the Completed Days from the task Duration and should NOT be entered.
Once the data has been entered the Gantt Chart is automatically generated. UPDATING EXISTING PROJECTS
Once the project has commenced the tasks completed can be updated in the data table in the corresponding “Completed” column. These changes will be automatically reflected in the chart where completed tasks or portions of tasks completed are show in green.
Customizing the Gantt Chart REDUCING THE NUMBER OF TASKS DISPLAYED IN THE CHART
The standard chart is set up to display 50 tasks. Where projects consist of less than 50 tasks, the excess tasks can be hidden and this will be reflected in an updated chart. To hide the excess tasks the following procedure should be followed:
Select the appropriate row by clicking on the row number in the workbook to the left of column A. Click on the row by using the right mouse button. Select “Hide” for the context menu displayed.
When required the same procedure should be followed to display tasks that have been hidden. In this case select unhide from the context menu. INCREASING THE NUMBER OF TASKS DISPLAYED IN THE CHART
The standard chart is set up to display 50 tasks. Where projects consist of more than 50 tasks, the additional tasks can be added. To add more tasks the following procedure should be followed:
Select any row by clicking on the row number in the workbook to the left of column A. Click on the row by using the right mouse button. Select “Copy” for the context menu displayed. Select the row where the new task is to be inserted by clicking on the row number in the workbook to the left of column A. Click on the row by using the right mouse button. Select “Insert Copied Cells” for the context menu displayed. Edit the task details in the new row as required.
www.businesstoolsstore.com Copyright © 2013 The Business Tools Store
3
8/29/2013 Note: The new task must be inserted in the body of existing table and can NOT be inserted after the last row at the end of the table.
www.businesstoolsstore.com Copyright © 2013 The Business Tools Store
4